The Trustees will provide an update following each Trustees’ meeting. Between meetings a considerable amount of work is undertaken by way of committees and this work will form part of the update.
22 April 2024 5BEL Trust update
Debrief from the most recent 5BEL Trust meeting including a status update on the project and arrangements to operate the train on the national rail network.
The Brighton Belle Trust met on April 22nd at Locomotive Services Limited, Crewe. Some significant changes were discussed meriting a comprehensive debrief for supporters and donors. The opportunity was also given to review progress with completing the train.
Composition of the Trust
Denis Dunstone, long standing chair of the 5BEL Trust who has steered the project from its inception through to the completion of a 4 car Brighton Belle train, stepped down as Chair of the Trust, as he indicated he would at this important stage. The Trustees appointed Ian Brown CBE FCILT as Chair. Additionally Reg Davies, who has assisted the Trust over the period of the restoration of the project has joined the Trustees as a member of the Trust. Stuart Wilkinson, a long standing Trustee, was appointed as Secretary.
Trustees agreed to invite Denis Dunstone to retain involvement with the Trust by appointment as a Vice President of the 5 BEL Trust. Denis has subsequently agreed.
The composition of the 5 BEL Trust is now:
Ian Brown CBE FCILT, Chair
Rev Stephen Baxter
Dr Reg Davies
Mike Hart, OBE
Douglas Lindsay
Dr Stephen Murfitt LLB, LLM , PhD
Stuart Wilkinson, Trustee and Secretary
Role of the Trust
The charitable status of the Trust has not changed. The 5BEL Trust is the owner of the train and a charity registered with the Charity Commission (number 1184057).
Th Trust is the holder of a contract whereby Locomotive Services Limited will operate the train. The Trust is responsible for the ongoing project to restore the train to meet the promise of a full 5BEL Brighton Belle Pullman train.
Status of the project to restore a four-car Brighton Belle as a fully restored train operating on the national rail network
Locomotive Services Limited has been restoring the 4 car train to a fully operational set at Crewe, capable of operating under its own power on the national network. The work is physically complete to a very high standard but some work needs to be completed in the area of insuring the loading gauge profile is correct and managing the weight distribution of the train before it can be tested. Commissioning the train will follow involving initially hauled tests on the main line, then later, tests with the train running under its own power. These tests will probably take place on the Crewe to Chester line and later on the electrified surface section of the Merseyrail network between Chester and Hooton.
Central Door Locking (CDL)
The Trust has agreed that the train will be fitted with central door locking prior to its introduction into service carrying passengers. This is not necessary during commissioning so it is currently envisaged that the train will return to Crewe for CDL fitment after completion of the commissioning programme.
The contract to operate the train commercially on the national network
The Trust has entered into a 10 year contract whereby LSL Ltd will operate the train as a self-propelled electric train with catering, at its own commercial risk as part of LSL’s portfolio. LSL has the skills and experience to do this, and the train fits well with LSL’s portfolio for charter trains of various configurations available to the public and corporate charters.
The contract provides for LSL to operate the train for two days each year to the requirements of the 5BEL Trust. The Trust will honour the promise that stakeholders and donors can sample the train early on in the programme. There will also be an educational element to this part of the programme to honour the requirements of our charitable trust status.
Restoring the train to a five car set-the 5BEL.
Up to this point, the Trustees have focussed on completing the 4 car train, maintaining the position that this must not be put at risk by embarking on further restoration work until the 4 car train is secure. The trust owns two further Brighton Belle cars plus three donor ex BR Southern emu vehicles with a large collection of spare parts and equipment. This has kept open the possibility of completing a five car train but continuing to keep such a large store of equipment is not financially viable. In fact it is a drain on our financial resources which if not attended to, potentially prejudices further restoration.
The Trust agreed with LSL at the meeting to explore the engineering feasibility of restoring a fifth BEL car. One car will be selected for this and one donor vehicle. The other body as well as the two remaining donor vehicles will be available to other heritage organisations. This will be accompanied by a rationalisation of our general spares, with LSL retaining any spares required to maintain the 4 car train in service, and the trust retaining those necessary for the potential 5th car restoration.
This puts the Trust in a position to focus on developing the 5th car project.
The launch of the fifth car project.
If the engineering appraisal deems the project feasible, The Trust envisages a relaunch of funding for the 5th car project coincident with the 4 car train being presented as ready for service, probably early next year.
Ian Brown CBE FCILT Chair, 5BEL Trust
18th May 2024
1 October 2024 5BEL Trust update
This is a summary of the Trustees meeting held on 1 October 2024.
- All Trustees were present with the exception of Stephen Baxter.
- The minutes of the previous meeting (22nd April 2024 were approved.
- It was noted that there had been no safety incidents to report since the previous meeting.
- The financial position was reviewed, as were the actions taken to reduce costs, viz:
Removal of the donor vehicle from Allelys to Peak Rail0
Scrapping of the two Mk I cars no longer required as donors
Assessment and consequent reduction in quantity of the spares held at Arlington - The detailed engineering assessment of the restoration of the 5th car is not yet complete, however a notional target figure of £1.5m was established for fund-raising purposes, fund-raising to begin when the restored four-car set appears on the network for testing (see below).
- It was agreed that the first commercial running of the four-car set will be between London Victoria and Brighton.
- Plans for the installation of Central Door-Locking are moving ahead, and it was noted that the inward-opening of the doors on 5BEL present a particular challenge.
- An application has been made to DfT for an extension of the current license for use of the Brighton Belle trademark.
- The Trustees will meet again on April 29th
5BEL Trustees Meeting Debrief. Meeting held at LSL Crewe October 1st.
- Following the Trustees’ meeting, the Trustees heard from Tony Bush, MD of Locomotive Services Ltd, on technical progress with the four-car set.Ride height and weight distribution problems have now been now resolved, to the satisfaction of ORR. The 70 volt systems have been successfully tested, as has the heating system.
- The commissioning programme is as follows:
During the first two weeks in November loco-hauled trials will take place between Crewe and Chester. This will allow monitoring of ride quality, wheel bearing temperatures etc.
Assuming that this reveals no significant problems, static testing on 3rd rail (Chester) with the shoes down, left connected overnight. Then first trials under own power will begin.
Assuming all goes well a Certificate of Attestation will be applied for, covering loco-hauled and own power operation. - Certification
LSL will write a Statement of Compatibility and send to Network Rail. If Network Rail is satisfied they will produce a Summary of Compatibility and issue it to LSL, who can then apply for paths to operate on the Southern Region.
The lease will become operative when LSL has both Certificate of Attestation and Summary of Compatibility.